Author Topic: can't move tasks in calender  (Read 4209 times)

andreas

  • Newbie
  • *
  • Posts: 11
    • View Profile
can't move tasks in calender
« on: December 12, 2009, 06:31:08 am »
Hello,

after a manual update from 1.53 to 1.6 i can't move tasks in the calender?
is this a bug, or a problem with my opengoo-installation?

Andreas

Pet

  • Global Moderator
  • Hero Member
  • *****
  • Posts: 638
  • Always mining for solutions!
    • View Profile
    • The Bet!
Re: can't move tasks in calender
« Reply #1 on: December 12, 2009, 05:01:09 pm »
To check whether it is a bug or not, just try the demo on the OG home page's menu. Moving a task works there.
Support OpenGoo - Sponsor a Feature! | Follow me on Twitter | OG Support Chat | Did you turn debugging on?

andreas

  • Newbie
  • *
  • Posts: 11
    • View Profile
Re: can't move tasks in calender
« Reply #2 on: December 12, 2009, 06:08:39 pm »
thanks for the hint.

it think, this is a bug. It's the same in the OG demo homepage.
Events can be moved.
If i move a task, then is it on the new date, but the task-date is not chanced!
(after reload, it's on the old date)

Andreas

RobertsWeb

  • Newbie
  • *
  • Posts: 3
    • View Profile
Re: can't move tasks in calender
« Reply #3 on: December 13, 2009, 05:53:59 pm »
I've seen a bug here as well. But for Events.

When I create an event for today, Sunday Dec. 13, 2009 at 4:00 PM to 6:00 PM and I am viewing the weekly view, I slide the event to Monday and the date changes to Monday just fine, but when I reload the page, the event shows up on Sunday again, even though the date says Monday as it should.

ignacio

  • Hero Member
  • *****
  • Posts: 1703
    • View Profile
Re: can't move tasks in calender
« Reply #4 on: December 14, 2009, 05:13:25 pm »
Seems that dragging tasks in the Monthly view has no effect, but it does work in the weekly view, right?

I wasn't able to reproduce your issue Robert.

andreas

  • Newbie
  • *
  • Posts: 11
    • View Profile
Re: can't move tasks in calender
« Reply #5 on: December 14, 2009, 06:28:27 pm »
Right. Dragging tasks works in the weekly view. Only in the monthly view is no effect.

RobertsWeb

  • Newbie
  • *
  • Posts: 3
    • View Profile
Re: can't move tasks in calender
« Reply #6 on: December 16, 2009, 12:23:35 pm »
Seems that dragging tasks in the Monthly view has no effect, but it does work in the weekly view, right?

I wasn't able to reproduce your issue Robert.

I must have been confused as well, as I cannot reproduce my issue either! Possibly previous javascript was being stored in my browser after update. I don't know.

Events seem to drag and drop fine.

However, I agree with the bug that tasks do not change date when dragged and dropped on a monthly view. They revert back to their original date when you refresh the page.

Murz

  • Full Member
  • ***
  • Posts: 147
    • View Profile
Re: can't move tasks in calender
« Reply #7 on: December 16, 2009, 02:15:18 pm »
Using opengoo 1.6 release, I can drag task start and finish dates via mouse on calendar monthly view, but this changes didn't saves to tasks! After refreshing I see the tasks in old places!