I can add a task which has due date even after due date of  milestone completion. why?

The due date for the task should not be after the milestone duedate ???
(if some one used M$. Pr0ject, they hav seen that assigning task with due date after due date for milestones is not allowed.)
~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~
|           If you don't succeed first time try try again.                  |
~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~*~

xtg

  • Newbie
  • *
  • Posts: 12
    • View Profile
Re: task due date and milestone due date
« Reply #1 on: November 12, 2009, 12:45:18 am »
OG is not a tool for scheduling tasks at first but a tool for documentation of the real work on tasks. You know that the scheduling of tasks and the realising of them often is getting a gap and getting still the necessity to get a reckoning. - Your problem seems for me looking like a candidate for a global setting.