Author Topic: Task dates 1 day before in task list.  (Read 6089 times)

eorama

  • Freshman
  • *
  • Posts: 17
    • View Profile
    • Email
Task dates 1 day before in task list.
« on: April 03, 2012, 02:48:11 pm »
Im in trouble with tasks

what I mean
if i set a task for starting 03/04/2012 and due date 03/04/2012 I will see it in my calendar as due on 02/04/2012

Any idea why happen this?

I have the latest 2.0.0.8 version
Community edition
« Last Edit: April 03, 2012, 03:46:41 pm by eorama »

eorama

  • Freshman
  • *
  • Posts: 17
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #1 on: April 04, 2012, 03:00:47 pm »
Any help on this?

rafj

  • Newbie
  • *
  • Posts: 5
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #2 on: April 04, 2012, 04:42:38 pm »
all dates are stored in GMT. Tasks are sterted on 00:00 local time but in table time is in GMT. so for it will be 22:00 day before.
In php code events have added local time zone when displayed. But tasks not. I will correct this for my purpose and everything is correct now.

eorama

  • Freshman
  • *
  • Posts: 17
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #3 on: April 04, 2012, 05:09:06 pm »
all dates are stored in GMT. Tasks are sterted on 00:00 local time but in table time is in GMT. so for it will be 22:00 day before.
In php code events have added local time zone when displayed. But tasks not. I will correct this for my purpose and everything is correct now.

Thanks for your Answer.

Could you post the fix here?

rafj

  • Newbie
  • *
  • Posts: 5
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #4 on: April 04, 2012, 05:44:28 pm »
OK. I will do it tommorow. But it will be fixed in next release anyway.
look at the bug reports  www fengoffice com/web/bugs/view.php?id=3883

eorama

  • Freshman
  • *
  • Posts: 17
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #5 on: April 04, 2012, 05:45:16 pm »
Thank you very much for your fast reply

rapheistos

  • Newbie
  • *
  • Posts: 2
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #6 on: June 08, 2012, 08:59:47 am »
Updated to Feng Office 2.1beta1 and the issue still exists!

start end due date always -1 days in the dashboard calendar view.

eorama

  • Freshman
  • *
  • Posts: 17
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #7 on: June 16, 2012, 05:30:03 am »
I have the same problem
No fix provided with the 2.1 beta

Any solution with dates?

franponce87

  • Administrator
  • Hero Member
  • *****
  • Posts: 1819
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #8 on: June 20, 2012, 10:25:11 pm »
The developer that replied this concern in the Mantis Bug tracker months ago confused it with another issue, which got solved as well.
I have made sure this matter was looked into again for this 2.1 RC, so please try again. I do know it happened with certain GMTs, but not with all, and it should be solved now. Otherwise, please let us know.

Thanks for your report and patience!

Best regards,
Francisco
Would you like to install Feng Office Professional or Enterprise Edition in your servers? No problem! Read this article!

choiceoutsource

  • Freshman
  • *
  • Posts: 28
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #9 on: June 26, 2012, 12:56:31 pm »
Still having the same issue. Not fixed here.

eorama

  • Freshman
  • *
  • Posts: 17
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #10 on: June 28, 2012, 09:28:39 am »
rc2 fixed the issue with dates for me

joko.nurjadi

  • Newbie
  • *
  • Posts: 3
    • View Profile
    • Email
Re: Task dates 1 day before in task list.
« Reply #11 on: July 18, 2013, 10:55:35 pm »
i'm using 2.3.1-rc and still have the bug.