Hi everyone. I am testing feng office with great results so far. Yes there are more sexy interfaces nowadays, like smartsheet, but the metaphor that Feng Office uses is still to me the most "natural" for my work.

I have a question though, in relation to tasks. I would like to have some ordering on tasks, as if they were dependencies. So far, the best method that I found was to use the old school WBS numbering at the beggining of the task  title, as in

010 - Project kickoff
020 - Agree project management methodology

And then I can use subtasks and repeat as necessary.  This way I can move tasks around by renaming the first part of the title, not that difficult to do really.

However I am wondering if there are any other was to manage tasks ordering and dealing with dependencies?