Since the upgrade to 3.0.7, some recurring tasks are not shown in the task view. However, they can be seen in the Overview tab.... so, they are simply hidden in the task view. This only appears to happen with recurring tasks.
-
Found them! The losts tasks were subtasks to a master task that was deleted. In prior versions, they just showed up, but in this version, they didn't until I removed the already deleted master task.
Easy fix!
-
Thanks for the confirmation Steve, and sorry for the late reply! (we read you found out how to quite soon heh!)
More improvements were done here in the latest versions too, so this should be working as expected once again. Otherwise please let us know about it :)